Solutions › Guides › Payload lead time

How long does a robot dog payload integration take, and what decides the lead time

Short answer: A standard inspection payload for a supported robot (Go2, B2, X30, Lite3, Husky, Scout, Hunter) takes 4 to 6 weeks from order to shipment, plus 1 to 2 weeks of transit and 1 to 2 weeks of site commissioning. The long poles are component lead times (a dual-spectrum gimbal or a specific LiDAR can take 3 to 5 weeks on its own), CNC or sheet-metal enclosure manufacturing, and the factory test. A payload for a robot model the integrator has not built for before adds 4 to 8 weeks of mount design and interface work. Custom sensors, certifications and software features are quoted separately and usually dominate the schedule when present. Ordering the robot and the payload together, deciding the sensor list early, and preparing the site map and points during the build are the three things that keep a project on time.
Updated 2026-11-05 · YUANZHI ROBOTICS engineering team

The question behind most first enquiries is not what a payload costs but when the robot can start working. The honest answer is a range, and the range depends on a few identifiable things: which robot, which sensors, whether the integrator has built for that robot before, what certifications are required, and how much the customer prepares during the build. This guide lays out the timeline stage by stage, explains what stretches and shortens each stage, and gives a planning template for a project.

3D render of a Unitree B2 with a YUANZHI inspection payload; a payload like this for a supported robot ships 4 to 6 weeks after order
3D render of a Unitree B2 with a YUANZHI inspection payload; a payload like this for a supported robot ships 4 to 6 weeks after order

The stages and their typical durations

StageTypical durationWhat drives it
Order confirmation and sensor list freeze1 to 5 daysHow quickly the customer decides; changes after this point restart the clock on affected parts
Component procurement2 to 5 weeks, in parallelGimbal, LiDAR variant, 5G router, battery certification; stocked sensors arrive in days
Mount and enclosure manufacturing1 to 2 weeks, in parallelCNC aluminium or sheet metal from existing drawings; new drawings for a new robot model add 2 to 4 weeks
Assembly, wiring and software installation3 to 5 daysStandard kits have a build sheet; custom sensor sets take longer
Calibration and factory test2 to 4 daysSensor extrinsics, thermal reference check, mapping and navigation run on the test floor, dock cycle, recorded test
Packing and export documents2 to 3 daysLithium battery paperwork, crates, certificate of origin
Transit5 to 10 days express, 4 to 6 weeks seaDestination, customs, battery shipping class
Site commissioning1 to 2 weeksMapping, inspection points, first rounds, operator training; remote or on site

Procurement and manufacturing run in parallel, so the elapsed time from order to shipment for a standard kit is 4 to 6 weeks, set by the slowest component. From order to a robot running rounds on site, 7 to 10 weeks is a realistic plan with express shipping.

What stretches the schedule

Payload designs for several supported platforms; a platform with existing drawings skips the design stage entirely
Payload designs for several supported platforms; a platform with existing drawings skips the design stage entirely

What shortens it

A planning template

For a standard kit on a supported robot with express shipping: week 0 order and sensor freeze; weeks 1 to 5 build, during which the customer sends site drawings, points and network details; week 5 factory test with a recorded video sent before the second payment; week 6 shipment; week 7 arrival and customs; weeks 8 to 9 commissioning and training; week 10 first unattended rounds. For a new robot model add 4 to 8 weeks at the front; for certifications add their laboratory time; for custom software run it in parallel from week 1.

Commissioning on site: stairs and doorways are walked under supervision during the first week before the robot runs rounds alone
Commissioning on site: stairs and doorways are walked under supervision during the first week before the robot runs rounds alone

What we commit to

Our quotations state the lead time per line item and the date the factory test video will be sent. The lead time starts when the down payment is received and the sensor list is frozen, which we confirm in writing. If a supplier slips, we tell the customer the same week with the new date and the option to substitute a stocked part. Commissioning time is quoted separately as remote hours or engineer-days on site, because it depends on the site more than on the payload.

If you are planning a project, send us the robot model, the sensor list and the target date for the first round; we will send back a dated plan showing what is on the critical path and what you can prepare in parallel.

FAQ

What is the lead time for a standard payload kit?

4 to 6 weeks from purchase order to hand-over to the carrier for a kit on a platform we already build for, assembled, calibrated and factory tested. Add 5 to 10 days for express transit and 1 to 2 weeks for commissioning on site.

Why can it not be faster?

Because the sensors are bought to order. A radiometric dual-spectrum gimbal, an industrial 5G router with the right bands, a specific LiDAR variant and a payload battery with certification each have 2 to 5 week supplier lead times, and the mount parts are machined after the sensor list is frozen. Kits that use stocked sensors (Mid-360, RealSense, Jetson) ship in 2 to 3 weeks.

What adds time?

A robot model we have not built for before (4 to 8 weeks for mount design, power interface and gait checks), sensors outside our standard list, a certification requirement (IP test by a laboratory, EMC, explosion protection), custom software features, and changes to the sensor list after the order.

Does the robot delivery time matter?

Yes. If the robot is ordered from the manufacturer at the same time as the payload, both usually arrive together; if the payload is ordered first, the robot's own lead time (2 to 8 weeks depending on model and region) becomes the critical path. We fit and test on the actual robot before shipment whenever it is available.

What can the customer do to keep the schedule?

Freeze the sensor list and the robot model with the order, provide site drawings and the list of inspection points during the build so that the route is prepared before the robot arrives, arrange the SIM card, network access and the dock location in advance, and name the operator who will be trained.

Configure your payload and get a quote

Get a quoteWhatsApp